September 20 ,2008
The Meadows at Wolf Run
Site Progress
WATER
The water lines are complete and ready for use and the sewer lines are finished .
SEWER
The sewer pump station is complete, all but the generator which will be complete by the end of September.
UTILITIES
PP&L electric, Windstream phone, and Comcast cable all are complete. PP&L gas lines are complete throughout the development. The installation of the gas lines down Cemetary Street to the current main in front of Hughesville High School will be complete by the end of October.
ROADS
All roads are graded and stoned and are easily drivable.
Home construction can start
at any time.
Continue to visit this page for further updates.
|
|